Equipment Installed Capacity
FIRM CAPACITY (THERMAL)  
Recip Phase 1+2 (6 Engines) 47.4 MW
Recip Phase 3 (4 Engines) 45.6 MW
Recip Phase 3 Expansion (2 Engines) 36.2 MW
Recip Phase 4 (6 Engines) 103.2 MW
Gas Turbine (GT) 20.0 MW
Total firm capacity 252.4 MW
   
RENEWABLES  
Wind Turbines (WP-Vaderpiet) 30.0 MW
Sunrise Solar Park 6.1 MW
Total renewables 36.1 MW
   
ENERGY STORAGE  
Battery Energy Storage System I (BESS I) 1 MW / 4 MWh
Average load demand (2026) 121 MW